Search
Close this search box.
 

City of Berkeley Bike Subcom meeting notes Aug 2009

Author: bcomadmin

Date: January 3, 2010

Berkeley Bicycle Subcommittee Meeting Notes

August 27, 2009

In attendance: Marcy Greenhut, Phil Morton, Dave Campbell, Eric Anderson, Claire Risley, Eric McCaughrin, Scott Mace

Staff Updates:

Ohlone Greenway: next Fall ’10 improvement complete. No changes for Curtis & Gilman

Bicycle Marking Maintenance: surveying being done and next year will be integrated into regular maintenance

Bikestation: work continues on design, project schedule needs to updated. New target is Bike to Work Day, 2010. Signage design is part of architects work. Wayfinding signage?

Bicycle Parking: 250 locations identified, installation starts Sept 09, $250-$300 each.

Safe Routes to School Grant Award: $900,000 for 4 schools, including the intersection of Virginia/Shattuck. No bike parking.

Safe Routes to Transit: application that includes improvements at two intersections, 1) Shattuck/Vine, and 2) Colusa/Solano. Application includes both bike/ped improvements. Awards announced November 09

Caldecott Tunnel Mitigations: no further update at this point.

Bicycle Boulevard Implementation

There was a lengthy discussion of Dave Campbell’s proposal to study designs for intersection improvements of boulevards with arterials. A berkeley bike map was studied and intersections identified that needed significant safety and access improvements. This list may be useful in developing intersection design options. There was consensus to make a recommendation to the Transportation Commission to direct staff to move forward on identifying consultant funding and start the process to develop designs for intersection improvements on the boulevards.

Adjournment at 6:30pm. Next Meeting: September 24, 2009, 5:00-6:30pm

Respectfully submitted,

Dave Campbell